A412 motorway Machilly–Thonon: route, works, timetable
Updated

The A412 motorway is due to link Machilly to Thonon-les-Bains over about 16.5 km. The environmental authorisation was signed on 28 August 2026 and work is under way, with legal proceedings still open.
This article reviews the procedure, the route, the appeals and what the project may change for property owners in the Chablais.
A major motorway project for the Chablais
The A412 is a motorway of about 16.5 km, designed to link the Bas-Chablais more efficiently to the A40, and beyond it to the Geneva region and the major national routes.
The project’s stated aims are several: improving traffic flow on routes that are saturated today, reducing daily journey times, making travel safer, and supporting the economic and residential development of the area.
The motorway is being built under a long-term concession awarded to AMEDEA, a concession company that is a subsidiary of Eiffage, financed by tolls.
Where does the project stand?
- 24 December 2019: decree declaring the project to be of public utility (published in the Journal officiel on 27 December 2019).
- 2024: the State grants the concession to the company AMEDEA (design, construction, operation, maintenance).
- 12 January 2026: the application for environmental authorisation is declared complete and in order.
- 20 April to 3 June 2026: public participation by electronic means.
- 18 May 2026: unanimous favourable opinion of the Haute-Savoie departmental council.
- 25 August 2026: favourable opinion of the CODERST (departmental council for the environment and health risks).
- 28 August 2026: the prefect signs the order granting environmental authorisation.
- Early September 2026: work starts four days after the order was signed, according to Batiweb. According to the same source, about 153 hectares of the 180 planned had already been cleared by the end of October.
- 27 October 2026: the liberty and custody judge of the Annecy judicial court orders the concessionaire to correct, within eight days, environmental failings (protection of beavers, fish rescue, devices to stop amphibians entering), on pain of a penalty of €20,000 a day. For the time being it refuses to suspend the works. The Annecy public prosecutor had requested the suspension on 21 October.
- 30 October 2026: the Lyon administrative court of appeal rejects the request to suspend the works filed by the City of Geneva and six Geneva communes. A decision on the merits is awaited and an appeal against the environmental authorisation has been filed.
The concessionaire announces entry into service in early 2029 (AMEDEA’s “Le calendrier” page). This timetable may change with the proceedings under way; we have not found a confirmed completion date for the works.
Technical characteristics of the A412
According to the December 2024 presentation, the project provides for:
- a 16.5 km, 2×2-lane motorway, with a 110 km/h limit, between Machilly (at the RD 1206) and Thonon-les-Bains (at the bypass),
- free-flow tolling, with no physical barrier: the vehicle is recognised under a gantry by its electronic toll badge or its number plate,
- three interchanges: Machilly, Perrignier and Anthy-sur-Léman,
- engineering structures, including 5 long-span viaducts and a rail bridge at Allinges,
- 45 wildlife crossings under the motorway,
- two car-sharing areas equipped with electric charging points, at Perrignier and Thonon-les-Bains,
- a 10 km cycle route alongside the motorway.
These elements aim to reconcile better travel with landscape and environmental integration.
A public and visible route
A video shows the precise route of the A412, commune by commune. It lets you locate where the motorway passes, identify the areas directly or indirectly affected and better understand the integration measures planned (noise barriers, structures, distances from homes).
Click here to watch the A412 route video
This transparency is useful to local residents, owners and future buyers.

Visualisation of the route of the A412 motorway between Machilly and Thonon-les-Bains.
Which communes are affected?
The link runs from Machilly to Thonon-les-Bains. According to the December 2024 presentation, the motorway also crosses ten communes: Loisin, Bons-en-Chablais, Ballaison, Brenthonne, Fessy, Lully, Perrignier, Allinges, Margencel and Anthy-sur-Léman. The agency follows the communes of its area (commune pages in French):
- Machilly: starting point of the link, with an interchange announced. The concessionaire has also announced the de-sealing of part of the leftover land along the RD 1206 to return plots to farming.
- Perrignier: interchange announced, exchange point for access to the cross-border regional train to Geneva, car-sharing area, and removal of level crossings no. 65 and no. 66 under the same scheme.
- Lully: the concessionaire says it has moved the route as close as possible to the edge of the forest, to the north, to limit the fragmentation of farmland.
- Allinges: a rail bridge was announced, at a cost of €25 million.
- Loisin, Ballaison, Bons-en-Chablais, Fessy and Brenthonne.
Margencel and Anthy-sur-Léman have no dedicated page on this site. An interchange is announced at Anthy-sur-Léman, and the Bois d’Anthy water catchment, which supplies drinking water to the Thonon area, is to be protected.
What was announced in December 2024
At the December 2024 presentation, the concessionaire put forward the following. They are repeated here as a reminder and may have changed since.
- Traffic: an announced fall of 40 to 50% on the RD 903 and of 10 to 20% on the RD 1005, to calm village centres.
- Toll: subscriptions for frequent journeys announced at −30 to −50%, and a further −20% for Crit’Air 0 vehicles.
- Environment: a sealed system to collect run-off water near the Bois d’Anthy catchment, a route avoiding the wetlands of the Margencel and Perrignier marshes, 3,000 metres of noise barriers near hamlets.
- Agriculture: about fifteen farms affected, with a collective agricultural compensation fund announced.
- Cost: €315 million announced at the time, including €25 million for the Allinges rail bridge. The concessionaire’s site now shows €340 million as the “amount of private financing”, without stating the total cost of the project.
A project that draws local opposition
Since its beginnings, the A412 has been contested by citizens’ groups, environmental associations and some residents.
The main arguments put forward concern: the impact on the environment and biodiversity, the loss of farmland, the mobility model favoured, and the effects on the landscape.
The Confédération paysanne called for the project to be stopped in a press release of 4 December 2024, pointing in particular to the loss of farmland and the cost of the project. This opposition also takes the form of legal appeals. In October 2026, the City of Geneva and six Geneva communes asked for the works to be suspended, which the Lyon administrative court of appeal refused. An appeal against the environmental authorisation is also under way. On the ground, the Annecy liberty and custody judge imposed wildlife protection measures on the concessionaire, and nearly 1,000 people demonstrated in Machilly at the end of September, according to Batiweb.
The debate therefore remains active, between mobility issues, development of the area and environmental concerns.
A412: what is at stake for local property?
The A412 works raise property questions for owners and future sellers in the Chablais.
An influence that varies with the situation
The impact on a property’s value depends on many factors: real distance from the route, visibility and potential nuisance (noise, views), planned noise barriers, improved accessibility for some areas, and local market dynamics.
In some cases, better accessibility can make an area more attractive. In others, immediate proximity to the route calls for a precise and nuanced analysis.
Why a personalised valuation is essential
A valuation carried out without taking the A412 project into account may be incomplete or inaccurate. Conversely, a professional analysis that takes in the real route, the timetable and the characteristics of the property makes it possible to: obtain a realistic market value, plan a sale, or simply see where you stand, without obligation.
Frequently asked questions
Where do the A412 works stand?
The environmental authorisation was signed on 28 August 2026 and work is under way. On 27 October 2026, the Annecy liberty and custody judge ordered wildlife protection measures without suspending the works. On 30 October 2026, the Lyon administrative court of appeal rejected the request for suspension filed by the City of Geneva. A decision on the merits is awaited.
Which communes are affected?
According to the December 2024 presentation, the motorway crosses, in addition to Machilly and Thonon-les-Bains, Loisin, Bons-en-Chablais, Ballaison, Brenthonne, Fessy, Lully, Perrignier, Allinges, Margencel and Anthy-sur-Léman. The links to the agency’s pages are in the “Which communes are affected?” section above.
Does the A412 automatically lower a property’s value?
No. The impact depends on many criteria: distance, real nuisance, planned protections and the overall attractiveness of the area.
Should you sell during the works?
Every situation is different. As the works are under way, the decision depends on the distance from the route, the timing of your project and the condition of the property. A valuation helps inform the choice.
Are properties several kilometres away affected?
Indirectly, yes. Improved access can change the attractiveness of some communes of the Bas-Chablais and the Collines du Léman.
Is a valuation chargeable?
No. The valuation offered by the agency Vue Lac et Montagnes is free and without obligation.
Does the valuation take the exact route into account?
Yes. It is based on the official route, the configuration of the property and the local property market.
Is your property affected by the A412?
Are you a property owner in the Chablais wondering about the value of your property near the route of the A412 motorway?
The estate agency Vue Lac et Montagnes offers a free valuation without obligation, which takes into account: the precise location of your property, the real route of the A412, the characteristics of your home and local property market data.
Communes close to the route (pages in French): Machilly, Ballaison, Bons-en-Chablais, Fessy, Loisin, Lully, Perrignier, Brenthonne, Allinges and Margencel.
Thinking of selling? Here are the steps of a sale, from purchase offer to deed of sale.
Request your free valuation or contact the agency.
Sources
- Haute-Savoie prefecture: Chablais motorway A412 (page updated 2 September 2026, in French)
- AMEDEA: A412 project site, “Le calendrier” page (in French)
- Haute-Savoie departmental council: press release of 18 May 2026 (in French)
- Batiweb: decision of 27 October 2026 on bringing the site into compliance (in French)
- LFM: suspension of works rejected, 30 October 2026 (in French)
- La Télé: suspension of works rejected, 30 October 2026 (ATS dispatch, in French)
- December 2024 project presentation, as reported by FranceBleu and Le Messager.
Conclusion
The A412 is no longer a project on paper: the environmental authorisation dates from 28 August 2026, work has started and entry into service is announced for early 2029, while legal proceedings remain open. For a Chablais owner, the effect on value depends on the distance from the route, nuisance and accessibility. Request a free valuation: we take the real route and timetable into account to give you a realistic market value.